MINUTES
OF MEETING
NORTH
SPRINGS IMPROVEMENT DISTRICT
The
regular meeting of the Board of Supervisors of the North Springs Improvement
District was held Thursday, September 5, 2002 at 4:10 P.M. in the District
Office, 10300 N. W. 11 Manor, Coral Springs, Florida.
Present
and constituting a quorum were:
Matt
Lauritzen President
Salvatore
J. Mendolia Secretary
Also
present were:
Rhonda K.
Archer Finance
Director
Dennis
Lyles Attorney
Donna
Holiday Recording
Secretary
Jane Early Gee
& Jenson
Roger Moore Engineer
Scott
Davidson WCI
Dave Rohal CCL
FIRST ORDER OF BUSINESS Roll
Call
Mr.
Lauritzen called the meeting to order at 4:10 p.m.
SECOND ORDER OF BUSINESS Approval of the Minutes of the Minutes
of the August 1, 2002 Meeting
Mr.
Lauritzen stated that each board member had received a copy of the minutes of
the August 1, 2002 meeting and requested any additions, corrections or
deletions,
There
not being any,
On MOTION by Mr. Mendolia seconded by
Mr. Lauritzen with all in favor the minutes of the August 1, 2002 meeting were
approved as submitted.
THIRD ORDER OF BUSINESS Public Hearing to Consider the
Adoption of the Water and Sewer Budget
Ms.
Archer stated we adopted our general fund budget, debt service fund budgets,
special operating budget for Heron Bay Commons and Parkland Isles and this is
the last budget we need to adopt to start the fiscal year on October 1. This is the water and sewer enterprise fund
budget and includes operations and debt service. We project our revenues next year will be
$9,037,386 that is down from this year's budgeted $10,452,925 and we expect to
see by the end of the fiscal year $7,968,431,
The largest discrepancy in what we budget versus what we actually
experience is in the development in the District, which is how many new units
come on line, what we projected to come on line versus what actually came on
line so far. It is not a problem because
we are still covering our expenditures but our revenues are lower year to date
than we expected. The debt service is
shown on page two with a total of $2,409,734.
On page three is the administrative budget and totals $468,410 and that
is up slightly from the prior year of $431,466.
The most significant increase is related to personnel costs and the rest
of the fees are fairly level or have gone down slightly. The largest expenditure in personnel costs
that we are experiencing is related to health insurance. We received a notice from our health
insurance carrier that they projected our insurance was going to go up 40%. We are researching and will be in a position
shortly to convert our health insurance to another company which is going to be
similar to the plan that our employees already have but a little less expensive
for the District and less expensive for the employees with dependent coverage
which is a payroll deduction for them.
We might be looking at a slightly higher deductible so that they can
afford to cover their dependents on the policy.
That is the case as well in plant operations. The personnel costs in plant operations have
gone up related to the health insurance but also related to hiring additional
personnel to operate the plant facility.
As we continue to complete our plant expansion and hire more personnel to
operate the different facilities in the different locations, we are adding more
personnel to the budget. Also this year
we added to the budget, our security line item.
The total plant budget is $3,125,025 compared to the prior year of
$2,376,329.
Mr.
Lauritzen asked are we able to refinance any of our bonds?
Ms.
Archer responded we are looking at that and it is something we are working
on. We will bring a proposal to you at a
future Board meeting.
The
field operations relate to the water distribution and wastewater collection
system that outside the gates of the plant facility. This includes the electricity for the lift
stations, trucks and field crews that work on the water and sewer lines. The field operations budget is $1,122.480 as
compared to this year's budget of $1,040,150.
Total operating expenditures in all departments of $7,180,285 compared
to the prior year of $6,285,524. Page 6
shows the projected surplus funds that we will generate this year, the debt
coverage, the balance remaining and keep in mind this excess is supposed to go
toward paying off a future bond issue that we should have been in a position of
issuing about this time in anticipation of the plant expansion that hasn't
started yet because the last plant expansion isn't finished. You can see we will not have a rate increase
to cover that future bond issue because we are generating sufficient revenues
with the user rate we have on our system.
If we need any type of rate increase for that plant expansion and future
bond issue, it should be slight considering we are generating surplus funds
right now to pay for that bond issue.
Mr.
Lauritzen opened the public hearing and there being no comments or questions
from the public, the public hearing was closed.
On MOTION by Mr. Mendolia seconded by
Mr. Lauritzen with all in favor the water and sewer budget for fiscal year 2003
was approved.
FOURTH ORDER OF BUSINESS Acceptance of the Audit for Fiscal Year
2001
Ms.
Archer stated a copy of the audit was provided to you prior to the meeting and
is for fiscal year ended September 30, 2001.
This is a clean audit as you can see in the report of independent
certified public accountants, the report on compliance and internal controls
and financial reporting, the report on bond compliance and the management
letter.
On MOTION by Mr. Mendolia seconded by
Mr. Lauritzen with all in favor the audit for fiscal year 2001 was accepted.
FIFTH ORDER OF BUSINESS Consideration of Plats
A. Mary Help of Christian Plat
Mr. Rohal pointed out on the map the
location of the Mary Help of Christian plat and stated they are going to expand
the facilities for a school. The bottom
one third of the property was platted as Parkland Heights, the center was
platted and the remaining third of the property is unplatted. We are combining all three pieces of property
into one plat. We are going through a
rezoning and small land use change at the city and county level so that we can
take some of the vested uses that we have and distribute them across all the property. The church will remain in its existing
location in the southern portion of the property and a school with grades K-8
will be constructed, a rectory and some day care facilities.
Ms. Archer stated our consulting
engineer did review the plat and provided a letter that was included in your
agenda package recommending approval and acceptance of drainage from the land
within the plat.
On MOTION by Mr. Mendolia seconded by
Mr. Lauritzen with all in favor the Mary Help of Christian Plat was approved.
B Parkland Western Community Park Plat
Ms.
Early stated they have already commenced the work on Parkland Western Community
Park and even though it is over 40 acres they can go right to South Florida for
a permit but North Springs still needs to look at their plans if they are
outfalling through a North Springs right of way. We also want to make sure they have 11.4%
surface water area. I did notify the
city engineer that they in fact did not have a permit from North Springs. I'm working with him and that is why we
stipulated that last paragraph. The plat
is fine we want them to be aware that we need to see those final plans.
On MOTION by Mr. Mendolia seconded by
Mr. Lauritzen with all in favor the Parkland Western Community Park Plat was
approved subject to the conditions listed in the engineer's review letter.
SIXTH ORDER OF BUSINESS Consideration of Permit Request for
Parkland Country Club Maintenance Area
Ms.
Early pointed out the Parkland Country Club maintenance area on the map and
stated this is a typical surface water permit and we recommend approval.
On MOTION by Mr. Mendolia seconded by
Mr. Lauritzen with all in favor the permit request for Parkland Country Club
Maintenance Area was approved subject to the conditions outlined in the letter
from the engineer.
SEVENTH ORDER OF BUSINESS Consideration of Work Authorization 94 for
Parkland Country Club and Engineering Design Agreement with WCI
Ms.
Early stated this work authorization is for the entire development and is for
the water and sewer design and the funding agreement is with WCI.
Ms.
Archer stated this is the usual two step process that we go through with a new
subdivision.
On MOTION by Mr. Mendolia seconded by
Mr. Lauritzen with all in favor Work Authorization 94 and the funding agreement
with WCI was approved.
EIGHTH ORDER OF BUSINESS Staff
Reports
A. Attorney
Mr. Lyles stated we are back at the
point in the year when we are up against local hearings on new bills for the
Legislative Delegation to take up and as you know our codification bill which
we are required to prepare and file did not get accepted last year and
therefore, was not acted on. I reported
to you then that we will be required to do it again this year and that is
coming up in October and we will dutifully submit our proposed codification
bill of all our special acts and amendments to the Legislative Delegation and
hope for the best from our local elected officials.
The issue that has caused a great
deal of staff effort to be undertaken both before the last meeting and before
this one is the continuing problem we have with our water plant expansion and
our contractor, Felix Equities which has been purchased by and is a subsidiary
of a national firm called Linknet. As we
reported to you last month, Linknet is in bankruptcy proceedings as of July and
we are continuing to have a severe problem with the contractor progressing with
the work and the subs and suppliers doing any work they contracted to do with
Felix Equities. They are essentially not
working or not working very much on the plant expansion. The basic issue is we are not getting the
plant completed in a timely fashion. We
have subs and suppliers unpaid who refuse to work or deliver equipment. Normally when you have that situation it is a
default under the contract and it would be except for the fact that we have a
bankruptcy proceeding. That stops us
from being able to demand that the surety come in and take over. All of us have been in communication verbally
and in writing with our opposite numbers at both the surety and the contractor
regarding the bankruptcy proceeding. The
surety has initially reviewed this claim they know is coming and they have
classified it as one where they do owe coverage to us and they have targeted it
as one they intend to come in and take over once the proper steps can be
taken. There are other jobs that Linknet
or Felix Equities is in the middle of that they are not going to accept
coverage on, there are defects in the notice or coverage or something but we
are not going to suffer that fate. We
are lined up and properly ready for the surety to take the job over and hire
another contractor or renegotiate something with Felix Equities to get the job
from here to the end. They can't do that
because of the bankruptcy proceeding.
The bankruptcy stops everything and it stops us as an owner of a project
even though we are a public entity from declaring the job in default which is
the step you have to take before you can bring in the surety. My last conversation with the bankruptcy
attorneys for Felix Equities was this morning and this afternoon, and it
appears that they are going to be able to get everyone involved from the surety
side as well as the contractor side to file with the bankruptcy court a motion
to reject our contract, meaning Felix will say formally they don't want to
perform the rest of the contract and that in effect sort of waives the
bankruptcy protections that they have and allows us to do what we need to do
with the surety but we have to involve the surety in every step of all of this,
otherwise, we run the risk of waiving the benefit of the surety. They have projected this job internally we
believe and their attorneys believe as a negative cash flow job. In other words if they had to complete the
rest of the contract, their position is that they will lose even more
money. They will ask to be let out of
the contract, bring in the surety to do what they need to do and that way they
will lose less than they otherwise might.
From our point of view they are not going to perform this contract, we
are all satisfied they are not able to perform and get the subs and suppliers
back on track with the right kind of payments and as of today we still have not
gotten the authority to issue two party checks made payable to Felix and the
subcontractor. They have to agree on how
the proceeds of that check will get divided before it actually gets
negotiated. It is a very complex
situation and we have all independently found out that nobody has run into
exactly this situation before. This is a
unique situation so we have a bit of a problem but we believe we have in place
a plan to get us from here to there. We
are hoping to get the final authority to file this motion and again it will
have to be Felix to file it. We are not
a party to the bankruptcy proceeding because we are not a creditor or debtor at
this point but we are an owner of a project and have a contract in play
here. With our urging and cooperation
they are going to court and file this motion to reject the contract. I would like you as a Board to pass a motion
indicating your approval of the filing of the motion to reject the contract on
behalf of Felix in the U.S. Bankruptcy Court.
On MOTION by Mr. Mendolia seconded by
Mr. Lauritzen with all in favor the Board approved the filing of the motion to
reject the contract by Felix Equities in U.S. Bankruptcy Court.
Mr. Lauritzen stated assuming that
happens are you ready to jump in with some bids?
Mr. Lyles stated it will be the
surety to get the bids and negotiate directly.
The surety will take the job over which is part of the coverage that was
paid for when the performance bond which is part of our contractual requirement
was put in place. They have to perform
under our specs. They can't provide us
with something different than what we contracted for. Our obligation is going to be to take the
remaining funds that we have in the construction account and pay it to the
surety.
Mr. Moore stated the surety has
issued one or two checks to Felix Equity.
Since the permits are all in Felix Equities name, I believe the surety
will come in with a new contractor and have a learning curve and expense to
take over the project but they will probably negotiate with some of the present
employees. They talked to some of those
people over a month ago. That will minimize
their loss. There is enough money left
in the pot that they will come out losing a minimal amount of money on this
job. On some of the other jobs the money
is gone, our money is still there. I
believe it will be a win/win situation if we can get over this one hump.
Mr. Lauritzen stated I feel we are
in a spot depending on them to do a good job.
Mr. Moore stated so far the quality
of the work is okay and we are 85% complete.
We have 15% of the funds left.
Mr. Lyles stated we don't have that
in hand yet but believe we will be there.
In case it doesn't work out, one thing that may occur is we may have to
file on our own behalf in the bankruptcy court a petition to release the stay
and allow us to declare the job in default and go through the technical steps
that we hope to avoid by doing it the way I described where they reject the
contract and get permission for the court and it goes right to the surety. If that doesn't happen we have to get a 15
day notice of our intention to declare default and a 20 day notice that it is
in default and a time to cure and those are all conditions in the surety
instrument itself that we are going to be facing and we hope not to face. To get to that point we may have to go into
bankruptcy court and file a petition.
There is a third possibility which would be a negotiated situation where
we would put our money into the court registry and allow the court to get
involved in the completion of the project and worry later on about who gets
what money as long as it is all deposited.
I request at this time to give staff authority if necessary bring in a
bankruptcy specialist who does this kind of work along with surety law work to
represent our interests. It would be a
quick and relatively inexpensive because we are not going to do a whole
bankruptcy proceeding. Everybody I have
talked to about this, all recommend that if we are going to go forward beyond
the point we are at we need to bring in a bankruptcy specialist to protect our
interests. I would like to be able to
bring in someone quickly and timely so we don't wait another month if
necessary.
On MOTION by Mr. Mendolia seconded by
Mr. Lauritzen with all in favor staff was authorized to retain a bankruptcy
specialist as outlined above if necessary, to report and ratify the fee
arrangement at the next meeting.
B.
Engineer
There not being any, the next item
followed.
C. Superintendent
Ms. Archer stated the county
contacted me and asked me to respond to an inquiry they had as to whether or
not we were implementing some type of review procedure for the water management
permits that we issue such as the five year renewal program we talked about a
few months ago. We will identify the
magnitude of the project and we will have that information for you at the next
meeting and how we will do a five review and renewal of those permits. The county is going to present to the
legislature again this year a bill requiring Districts to adopt a five year
renewal program or they will step in and do it themselves. We will have that on your next agenda for
consideration.
NINTH ORDER OF BUSINESS Supervisor's Requests and Audience
Comments
There
not being any, the next item followed.
TENTH ORDER OF BUSINESS Approval of Requisitions and Invoices
On MOTION by Mr. Mendolia seconded by
Mr. Lauritzen with all in favor the requisitions and invoices were approved as
submitted.
On MOTION by Mr. Mendolia seconded by
Mr. Lauritzen with all in favor the meeting adjourned at 5:05 p.m.
Salvatore
J. Mendolia Matt
Lauritzen
Secretary President