MINUTES
OF MEETING
CORAL
SPRINGS
IMPROVEMENT
DISTRICT
The regular meeting of the
Board of Supervisors of the Coral Springs Improvement District was held on
Present and constituting a quorum
were:
Bob Fennell President
Bill Eissler Vice
President (by phone)
Glen Hanks Secretary
Also present were:
Doug Hyche District
Staff
Mel Entus
Mike Acosta
Dennis Lyles Attorney
John McKune Engineer
Mr.
Petty called the meeting to order and called the roll.
SECOND ORDER OF BUSINESS Approval of the Minutes of
the December 12, 2005 Meeting
Mr. Fennell stated each Board member
received a copy of the
Mr. Hanks stated on page three, Mr.
Petty stated “a work order is prepared by an agent who reviews the situation
with staff”. Are you referring to FEMA?
Mr. Petty responded FEMA or the
NRCS.
Mr. Lyles stated on page 11 where I
said, “there is nothing associated with this number”, the comma should be
deleted. The intent was to say there is
nothing associated with this number to make this a binding agreement. On page 20, in the paragraph before the
motion box, the sentence “this is truly a bonus in the sense of a gift” should
be “this is not truly a bonus in the sense of the gift”. The motion was in recognition for additional work
and effort performed. All of the
employees worked hard during Hurricane Wilma but we specified the bonus was for
additional work performed by two employees.
On MOTION by Mr. Hanks seconded by Mr. Eissler with all in favor the minutes of the
THIRD
ORDER OF BUSINESS Report
from Mr. Eissler on District Accounting Procedures
This
item was tabled until the next meeting.
FOURTH ORDER OF
BUSINESS Consideration
of Change Orders
A. Change
Order No. 1 to Benson Electric, Inc. for a Lighting and Surge Protection System
for a Net Decrease of $15,775.96
Mr. Fennell asked is the decrease
because of work we did not want performed?
Mr. McKune
responded yes. We decided there was one
area around Plants C&D we did not want the contractor to work in. This is a deduction from his contract. We went back and forth with the contractor
three times until we agreed on this amount.
Mr. Hanks stated there was a small
addition for a requested start delay.
Mr. McKune
stated this is a penalty for delaying the contractor from starting their work.
On MOTION by Mr. Eissler
seconded by Mr. Hanks with all in favor Change Order No. 1 to Benson Electric,
Inc. for a Lighting and Surge Protection System for a Net Decrease of $15,775.96
was approved.
B. Change
Order No. 4 to Intrastate Construction Corporation for Wastewater Plants C and
D Rehab for a Net Increase of $289,384.22
Mr. McKune
stated if you recall, two or three months ago, we had several conversations
regarding the injection well pump station.
We recommended at the time obtaining a new pump to replace the three
original pumps, which have been in place for 25 years. This pump was needed to provide necessary
backup to the recently installed Pump Station 2. Since there was no existing contract for the
pump, we decided to award the contract.
The pump has been delivered and is in the manufacturer’s warehouse
within the city of
Mr. Petty asked is this pump replacing
the three older pumps?
Mr. McKune
responded yes.
Mr. Petty asked is it acting as a
backup to Pump Station 2, which handles most of the flow?
Mr. McKune
responded yes.
Mr. Petty asked is it difficult to
obtain parts for these older pumps?
Mr. McKune
responded yes.
Mr. Hanks stated I understand your
concerns about not having contractors stepping over each other but the cost is
almost $300,000. Can we go out for
bids?
Mr. Lyles responded one of the
reasons staff is bringing this forward as a Change Order is because this is
part of a contract, which was bid. When
we do a Change Order, we are holding the unit prices to the original bid
prices. The expectation from staff’s
point of view is if you were to put this out for bid, it would receive a lower
price than when we bid this contract.
The issue with the pump and having to put it out for bid is a different
set of circumstances. We will still receive
the sales tax exemption. The bottom line
is we did this with the idea of saving money and prevent having two contractors
working at the same time.
Mr. Hanks stated I understand. However, at a certain point you have to say,
“we should look at the dollars”.
Mr. Hyche
stated it is always kept in our minds.
As Mr. Lyles said, we have unit pricing specifically for labor and the
materials are on-site.
Mr. Petty stated this is a good
suggestion. However, if we go out for
bid, I am afraid we are going to lose the existing contractor because they will
be moving off-site and will no longer be able to honor the Change Order. Therefore, we are recommending approval. Your points are well taken.
Mr. Fennell asked what needs to be
done?
Mr. Petty responded as an old
Operator, those systems from the 1990’s were junk in 1992 because we could not
get the water down fast enough and Pump Station 2 was built in a rush. Those pumps do not exist anymore. Trying to purchase these parts is like going
to
Mr. Fennell stated why are we
spending $300,000 for a $36,000 pump?
Mr. McKune
responded we have a concrete building with three pumps and all of the piping,
controls, electrical cabinets and pressure devices. The three pumps need to be removed and the
piping needs to be revamped to accommodate the new pumping arrangement. To show you how these dollars add up, the
backup to this Change Order involves 13 items.
Item one concerns the office overhead, which the contractor can
rightfully put into the contract while items two through four deal with the
demolition of the existing pumps, piping and all electrical.
Mr. Fennell asked why do they need
to be demolished?
Mr. McKune
responded the three pumps have not worked for quite some time and by permit, we
need to demolish them.
Mr. Petty stated the problem is if
one pump breaks down, we are back in emergency mode because we cannot get the
water down deep enough. Therefore, for
reliability purposes, your engineer is recommending a backup pump for Pump
Station 1.
Mr. McKune
stated this is a condition of our permit.
Mr. Petty stated it is not unusual
for a pump to break down and need repair.
We have time to do due diligence.
Therefore, if the Board wants to put this out for bid, we have the time
to do so. However, in order to comply
with our permit in a timely manner, we should do this now.
Mr. Hanks asked what are the
consequences for failing to comply with the permit?
Mr. McKune
responded the consequence is discharge into the canal, which is in our permit
as an emergency discharge location. The
state would not look kindly on a discharge of this nature simply because
organically, the District has the third pump.
This is part of the reason for accelerating this program by installing
the pump as soon as possible.
Mr. Petty stated Mr. McKune is coming to you with capital projects he feels has
the most exposure at this time. He
believes this is next great level of exposure.
Mr. McKune
stated items five through seven deals with the addition of new piping valves
and necessary tie-ins to the existing piping.
Mr. Hanks stated these items alone
total $120,000.
Mr. McKune
stated items eight and nine deal with the installation of the new pump and
performing start up procedures.
Mr. Fennell stated the $6,000 charge
for installing the pump makes sense to me.
What you are saying is the pump itself is not expensive but rather everything
concerning the connection of the pump and disposing of the old interconnectives.
Mr. McKune
stated most of the expense is to make the system work. Item 10 is for the replacement of the steel
work adjacent to and across the top of the Pump Station. It is dangerous to walk across the walkway because
you have to put your feet on the side rails and there is a risk of one leg falling
through. This walkway needed to be
replaced for quite some time.
Mr. Petty stated in the past, part
of the operating procedure was to hand carry powder chlorine to the clear well
whenever there was contamination. This
was a standard procedure imposed by DEP.
Of course powder chlorine is going to get on the steel and if the steel
was moist, it created a corrosive atmosphere.
Mr. McKune
stated item 11 deals with the changes to the electrical and instrumentation and
is paid directly to the Electrical Sub-Contractor. Item 12 concerns some miscellaneous work and
item 13 deals with the overhead, markup and sales tax; at the percentages
stated in the contract price. All of
these items total $289,384.22.
Mr. Hanks stated a good portion this
Change Order is for valves.
Mr. McKune
stated valves are very expensive. One 24
inch valve can range from $15,000 to $18,000.
Mr. Petty asked is the standard pressure
130 psi?
Mr. McKune
responded the standard back pressure is 35 psi. These are high volume pressure pumps.
Mr. Petty asked was Pump Station 1
giving us all of the back pressure?
Mr. McKune
responded it was about the same.
Mr. Hanks asked is this part of the
capital improvement program?
Mr. McKune
responded yes.
On MOTION by Mr. Hanks seconded by Mr. Eissler with all in favor Change Order No. 4 to Intrastate
Construction Corporation for Wastewater Plants C and D Rehab for a Net Increase
of $289,384.22 was approved.
Mr. Fennell asked do you have any
further information on the audit?
Mr. Petty responded we have several
calls into our auditor who the Board authorized to do an in-house special audit
not to exceed $10,000. Ms. Janice Larned
is currently working on this since we are having trouble getting a hold of the
party responsible for defining the work from the auditor. If we do not have anything in the next day or
two, we will go over to his office.
Mr. Fennell stated please call me if
by the end of the week the audit has not occurred.
Mr. Hanks asked when did we direct
him to do this audit?
Mr. Petty responded at the November
meeting. Part of the reason is the
change in management from Mr. Pete Witschen to me. I take the blame for the delay. Mr. Eissler is
supposed to work with the auditor when he begins to define those services.
FIFTH ORDER OF
BUSINESS Staff
Reports
A. Attorney
Mr. Lyles stated I have no report.
Mr. Hanks asked is there anything new
on
Mr. Lyles responded everything is
moving along smoothly.
Mr. Fennell asked do we have any
information from our lobbyist on legislative issues concerning the
District.
Mr. Lyles responded I will contact
our lobbyist and discuss the current legislative agenda on any matters
affecting the District.
B. Engineer
1. Monthly Water & Sewer Charts
Mr. Petty stated the charts and work
orders were presented to the Board today as we were working on the design of
the graphs. We will send a package to
Mr. Eissler after the meeting.
Mr. Eissler
asked what is the color of the water?
Mr. Entus
responded the color on the discharge system water is between 10 and 12.
Mr. Eissler
asked what about the hardness?
Mr. Entus
responded the hardness is 80 to 90.
Mr. Hyche
stated the average is 80
Mr. Fennell stated we received two
new charts, one for wastewater plant infiltration chart and the other for water
line loss.
Mr. Petty stated these charts were
part of a single chart the Board used to receive showing water and wastewater treatment
flows and rainfall. Over the years the
chart became so complex to the point where I could not understand it and I was
the one who started this in the early 1990’s.
The intent of graphing this was to determine the water line loss and the
infiltration to the wastewater treatment plant.
We separated the information and compared it to each other. We feel this is a more comparable format so
you can see exactly what we are trying to see.
The good news is the water line loss is at 4.1%, which is considered
excellent in the industry. Water line loss
of less than 5% is considered excellent while less than 10% is considered
average for the processed water, which is passed through the meter. This is considered to be what we refer to as
a water audit and a very fine evaluation.
We are very proud to show you this number.
Mr. Fennell stated it looks like
there is a discrepancy on the line chart compared to the infiltration chart. If I do a quick comparison of wastewater
treated water for Pump 7, it looks like the water billed is 120 mg while the
wastewater treated is 150 mg, for a difference of 30 mg.
Mr. Hyche
stated one line is water to water and the other is water to sewer.
Mr. Petty stated the graph with the
single blocks is analyzed because billing dates can be every 20 days or 40 days,
according to DEP regulations. Instead of
showing you lines crisscrossing for no apparent reason other than the billing
dates not matching, we analyzed it and put in a whole year’s flow.
Mr. Acosta stated it may be 20% one
day and nothing the next day or 5% day in and day out.
Mr. Petty stated this will be a
rolling, annual graph.
Mr. Fennell asked why is one
outgoing as opposed to incoming?
Mr. Hyche
responded you need to focus on the red line which is the incoming line.
Mr. Petty stated the number has
improved over time as the repair efforts have brought it down. You still have infiltration in the sewer
system. What this graph shows is
rainfall you are now getting a column of water along the line break or wherever
the infiltration is occurring, causing a great deal of infiltration. In December, January and February we can have
very low rainfall amounts and you will still see infiltration. This proves the water is coming from the
groundwater table and not so much from a rainfall event. We have lateral pipe issues because of the
camera inspections. Our engineer and Mr.
Hyche have a great deal of history. This is starting to get to a manageable
percentage as we are starting to get the lines closer together. This is well within industry tolerances.
Mr. Fennell stated we had a 4% loss.
Mr. Petty stated it is considered to
be excellent.
Mr. Fennell asked what would a 4%
loss be attributable to?
Mr. Petty responded fire hydrant
use, flushing of lines, small diameter leaks coming through the joint fittings,
sweating of the pipe, unmetered sources we do not
know about or illegal taps.
Mr. Acosta stated when new projects
go in; we are required to test the lines.
We are not required to achieve zero leakage, but a set amount per
inch. You do not have a water tight
system.
Mr. Fennell stated we have two
choices; we can either increase the size of our processing plant for wastewater
to the point where we are getting comfortable or relay all of the lines. It sounds like we are in good shape and it is
not worth our time to do any more work to these pipes.
Mr. Acosta stated we can refocus
some of our efforts on producing infiltration and change in tap, relining the
pipes or installing rain guards on some low lying manholes.
Mr. Petty stated the program we have
done from year to year, which is to fix whatever lines we see, has been showing
an improvement. You keep doing this
because you have the workers, the equipment and it is in the budget. You have a program for fixing laterals, which
are broken from being mowed over so many times.
I do not know whether or not you need a new program. Mr. McKune has
focused on two key issues, which is to refurbish Plants A & B. The effectiveness of treating this small
percentage difference of infiltration is going to be much cheaper than trying
to replace the line.
Mr. Acosta stated we have a
permitted tank capacity and fixed number of gallons per day at the amount of
plant capacity we have to run. We have
the ability to take plants off line while still having the ability to keep
these plants running 24/7 regardless of the flow. Does it make a difference in our operating
costs to reduce the infiltration any further if you have the plant
capacity?
Mr. Petty responded under certain
conditions, as an operator, Mr. Hyche has a few
options available to him such as doing a quick start of the plant by dumping
digester material. Is he going to
receive premium treatment at the time?
No, but he will meet the regulations.
We are talking about instances where a Tropical Storm dumps 10 inches of
rain in a 24 hour period and people start popping manholes in the street in
order to get the street drainage down.
We get a great deal of water and Mr. Hyche
would do what I just described or something similar. The plant’s carrying capacity and the tankage itself gives you many options for not only repairs
and maintenance but also surge conditions.
Repairing the lines is something we should stick to. We have taken care of all of the easy items
over the last 15 years and you are now trying to do the tough items where for
every dollar spent, you do not get a dollars worth of savings.
2. Utility Billing Work Orders
Mr. Fennell stated we received the
utility billing work orders and there is nothing unusual other than having many
mis-reads in November. Is this because of the hurricane?
Mr. Petty responded these were the
corrections we authorized for damages caused by trees pulling lines out of the
ground.
Mr. McKune
stated I provided to the Board a letter I sent to Mr. Petty, which reads as
follows:
“Enclosed is
the request from Intrastate Construction Corporation for payment in the amount
of $154,819.15, representing work performed on an emergency basis to clear
downed vegetation and trees from the CSID Utility Plant site. This work was approved as eligible for
reimbursement by Mr. Dimitri Ousakalides,
the FEMA representative.
Based upon
recent information regarding the FEMA and NRCS reimbursements, it may be quite
some time until reimbursement monies are made available to CSID. Consequently, I feel that the District should
favorably consider making payment to the contractor prior to finalization of
the federal reimbursement process.
Intrastate
utilized a subcontractor to help with some of the removal process so that the work
could be accomplished rapidly. He
understandably expects to be paid within a reasonable amount of time.
I recommend
CSID make payment to Intrastate Construction Corporation in the amount of
$154,819.15. Please give me a call if
you have any questions.”
This represents the work performed
during the month of November. Without
doing this, there was a good possibility the canal on the south side of the
plant site would have overflowed into the plant. We also had a leak on one of the well water
line crossings, which we were concerned about and we needed to clear fallen
trees in order to get access to the line.
We also needed to provide access for all chemical deliveries of the
sludge removal trucks to keep this plant operating. In my opinion, this work helped us to provide
water to the City of
Mr. Petty stated I looked over the
bill and spoke with Mr. McKune regarding this
matter. It is my opinion, while the
number is high for the time the services were applied; it is a reasonable number
and was needed to keep the plant running during Hurricane Wilma. This is a contractor who kept his equipment
and manpower onsite stabilizing the situation so our guys could stay.
Mr. Fennell stated there is one bill
for $69,070.65 and another for $85,748.50.
Mr. McKune
stated one was for the subcontractor and the other was for the main
contractor.
Mr. Petty stated the subcontractor
concentrated mainly on landscape removal onsite with all of the damaged
trees. They performed in groups of six or
eight, picking up the tree limbs.
Mr. Hanks asked how many trees fell
down?
Mr. McKune
responded hundreds.
Mr. Petty stated they were not our
trees as much as trees from across the canal, which fell onto our property.
Mr. McKune
stated we removed some Australian Pines lying on top of the large storage
tank. There are sufficient surplus
monies in the account to cover this request.
Mr. Petty stated the FEMA
application is for facility cleanup.
Mr. McKune
stated there are two federal programs; one for the repairs and cleanup
necessary within the plant site and the other for canal debris cleanup.
Mr. Fennell asked when are we
getting money from FEMA?
Mr. Petty responded we should be
seeing the money within 60 days. In the
meantime, we have sufficient funds to cover the request. When we first discussed this matter with
them, the expectation was for receipt of the money in two or three weeks.
Mr. Eissler
asked when how do they bill us?
Mr. McKune
responded this was billed on man-hours worked and equipment used on a typical
time and material basis.
Mr. Eissler
asked have you looked over this request?
Mr. McKune
responded yes. The contractor has a
summary sheet indicating approximately 1,300 man-hours worked.
Mr. Fennell stated they have numbers
for what they are charging. What you do
not know is how many hours they worked.
Mr. Petty stated at the time of the
work being done, it met the FEMA levels and did not exceed them. The work was performed expeditiously so the
plant could stay up and running. I think
we did well by having a local contractor.
Mr. Eissler
asked who follows up with FEMA?
Mr. McKune
responded I will and so will Mr. Petty.
Mr. Fennell stated at the last
meeting, we were discussing having someone follow this money. Who is this person?
Mr. Petty responded I am doing this
as the manger with Mr. McKune. Mr. Hyche has been
doing all of the work and the rest of us are worrying.
Mr. Fennell asked do you have
someone from the Accounting Department tracking this money?
Mr. Petty responded not until we
start receiving monies. Until this
happens, we have our engineer who is an expert in quantities in cost as our
compliance officer.
Mr. McKune
stated the remainder of the canal cleaning work, which will take some time,
will be bid on a lump sum project basis.
FEMA will pay based on time and materials but only during the initial
emergency. Time and materials by and
large over a large program is hard to control and it is very easy to let it get
out of hand unless you are there monitoring the activity of every piece of
equipment and individual on the job. We
know the prices for doing this type of work and FEMA and the NRCS are in
agreement with us. We will find precise
areas where the work needs to be done to end up with one lump sum. Therefore, we will not need the District Accountant
to track this because it is simply a monthly draw against the percent to
complete. It should be much easier to
control.
Mr. Fennell asked other than the
work done onsite, have you started the canal work?
Mr. McKune
responded no.
Mr. Petty stated other than staff
using pickup trucks and chain saws.
Mr. Fennell stated in four months we
will be into the next hurricane season.
I do not think we are moving along quick enough.
Mr. Petty stated we can move along
quicker by spending more.
Mr. Fennell stated we authorized you
to go out for bid a couple of months ago.
Mr. Petty stated we had to build the
specification, in the hope of piggy backing the City of
Mr. Hanks asked when we were looking
at piggy backing the city’s contract, should we have reviewed the
specifications before we gave the approval to piggy back onto the contract?
Mr. Petty responded we had hoped to
piggy back their contract.
Mr. Hanks stated it should have been
done and we should have made sure the contract was sufficiently detailed. We lost the chance of taking care of the
trees because the city’s contract did not cover enough detail. It only covered particular line items. Is this correct?
Mr. Petty responded yes.
Mr. Fennell asked what does it take
to obtain specs for Phase 2?
Mr. McKune
responded the specification would require the addition of root removal and
repairs of the canal banks. It would
take a week to put those specifications together but two weeks to identify each
of these locations where work needs to be done.
I still need to prepare a set of plans indemnifying the scope of the
work. To the Phase 1 map, we would add
quite a few thousand feet of Phase 2 canal bank restoration. Phase 1 removes the trees and roots. There are some trees blocking the flow and to
get to them, we need to remove 2,000 feet of trees from across the canal.
Mr. Fennell asked how much money are
we talking about?
Mr. McKune
responded we have an estimate for Sunshine from the NRCS, which can be used for
CSID. For Phase 1, the cost is
$460,000. Because Sunshine has more
trees than CSID, their total estimate from the NRCS is $4,200,000. Based on your criteria, the total amount for all
of Phase 1 and Phase 2 within CSID is $3,000,000.
Mr. Fennell stated we need to
proceed with Phase 1 and the specifications for Phase 2 need to go out as soon
as possible. Please let your staff know
we are interested in expediting this.
Mr. McKune
stated this is underway as we speak.
Mr. Petty stated in regards to how
we will pay for it, we have prepared a financial plan and are waiting for the
bid numbers. We plan to have all of this
before the next meeting and will present a cashflow
presentation with the cost, options and recommendations from staff.
Mr. Fennell stated we definitely
need to know the cashflow because we spent $154,000
and have not received any money from FEMA.
For a small company like us, spending money from our pockets presents
some problems.
Mr. Petty stated you also have
engineering costs, which we are incurring.
Staff has already worked the overtime.
Mr. Fennell asked when do you plan
to go out for bid on Phase 1?
Mr. McKune
responded hopefully next week.
Mr. Fennell asked when will Phase 2
go out for bid?
Mr. McKune
responded we need further definition from NRCS.
Mr. Petty stated the Phase 2 specifications
should be available for your review, acceptance and authorization at the next
meeting.
Mr. Fennell stated we cannot wait
this long. We need to shoot for two
weeks. We already authorized you to go
out for bid a couple of meetings ago. We
will not hold you up. What will hold you
up will be your own efforts.
Mr. Petty stated we will go out for
bids on Phase 2 as soon as the specifications are prepared. Mr. McKune plans to
have those specifications completed in the next 10 to 14 days.
Mr. McKune
stated I recommend structuring the bid so Phase 1 is identifiable and Phase 2
is an additional item.
Mr. Petty stated good point. This would give the Board two options.
Mr. McKune
stated we can do Phase 1 definitely and Phase 2 as an alternate, which can be
included into the bid 90 days prior to award.
This gives us the most flexibility.
Mr. Petty stated this gives you the
ability to act fairly quickly.
Mr. Fennell stated do it the way you
want to but do it quickly. I would like
to have a call in two weeks from Mr. Petty informing me everything was sent
out.
Mr. Hanks stated when we draft the
specifications; we should make sure there are time constraints to perform the
specifications.
Mr. McKune
stated we will specify the time of performance in the specifications.
Mr. Fennell stated our goal is to
complete this by June. Please tie in
your PR with the bids. Before you send
out the PR, please provide it to me for review.
Mr. Petty stated we will provide it to
the Board for comments.
Mr. Fennell stated the plan is
within two weeks; we will get the bids out and have a written PR statement.
Mr. Petty stated at this time, we
need Board approval of the request from Intrastate Construction Corporation.
Mr. Hanks stated they requested $36
an hour for a chain saw and $60 an hour for a Crew Foreman.
Mr. Petty stated it all seems so
reasonable within 48 hours of the storm.
Mr. Hanks stated it was not within
48 hours. The work was performed on
October 31st, which was a week after the storm.
Mr. Fennell stated I do not think we
have any choice. We would feel better
about the bill if we saw some money coming from FEMA. When I applied to FEMA, I received my funds
within a week. They actually wire
transferred the money to my account.
Mr. Acosta stated we have the
paperwork for the facility portion. We
just need the invoices so we can submit to FEMA.
Mr. Hanks asked do we have
sufficient funds to cover this request?
Mr. Petty responded in the water and
sewer utilities, you have over $7,000,000 in your account aimed for capital
improvements. We should be able to
handle it.
Mr. Hanks stated it is better to
have the funds taken from the Utility Budget rather than the Stormwater Budget.
Mr. Fennell stated it is fair since
most of the expenses are utility related.
On
MOTION by Mr. Hanks seconded by Mr. Eissler with all
in favor the request from Intrastate Construction Corporation in the amount of
$154,819.15 for work performed on an emergency basis to clear downed vegetation
and trees from the CSID Utility Plant site was approved.
Mr. McKune
stated I provided Work Authorization 28 to the Board for CH2M-Hill to proceed
with the canal cleanup efforts, which we have been doing. Up until now, we have been charging our time
to the engineering line item of the budget.
It is rather unidentifiable doing it this way. Approval of this Work Authorization allows us
and the Board to keep track of the dollars associated with the cleanup.
Mr. Petty stated it is also
quantified for FEMA reimbursement as well.
Mr. Eissler
stated it seems reasonable.
Mr. Fennell asked is the cost
$25,000 a month?
Mr. McKune
responded up to $25,000.
Mr. Petty stated we are asking the
engineer to perform the contract onsite for FEMA, which required actions such
as taking photographs of every tree and verifying GPS locations. We can have as many as four employees onsite
during working hours.
Mr. Fennell asked do you have the
man-power?
Mr. McKune
responded we have 200 man-hours.
Mr. Fennell stated we are probably
talking about $1,000,000 to $3,000,000 worth of submittals and we have to make
sure it is done correctly.
Mr. Petty stated some contractors
are saying they will get it done in 30 days, while others are talking about 60
to 90 days.
Mr. Fennell asked where will the
funds be taken from?
Mr. Petty responded the General Fund
where you have $1,083,106 in reserves for fiscal year 2006. We are very confident we should get through
this without any difficulties. At the
next meeting, we are going to bring several options before the Board, all of
which project a fairly flat cashflow issue.
On
MOTION by Mr. Hanks seconded by Mr. Eissler with all
in favor Work Authorization #28 with CH2M-Hill in the amount of $25,000 for
post-hurricane water management system rehabilitation was approved.
Mr. Hanks asked how are we looking
overall? The estimate of $1,000,000 was
quoted at the last meeting.
Mr. Petty responded this was the
first estimate from Arbor Tree.
Mr. Hanks stated I am disappointed for
not having more estimates.
Mr. Petty responded I had not
prepared the book yet because I wanted the specific numbers. However, I can speak to the financial theory
and policies.
Mr. Hanks asked can you bring forth
some generalities?
Mr. Petty responded yes.
Mr. McKune
stated some of the work has already been done.
We hired contractors, which we thought were efficient than we thought or
NRCS thought they were. Arbor Tree has
their own contractor with SFWMD to do this type of work and equipment
specifically for this purpose. They can
move fairly quickly as long as they have access to the trees.
Mr. Fennell stated there must be
competition with every other group in
Mr. Petty stated there is now.
Mr. McKune
stated they did not have as big of a backlog.
Mr. Fennell asked how much of the
$3,000,000 can we get out of FEMA and other groups?
Mr. Petty responded we do not want
to speculate. We had a prior commitment
of $410,000 to $420,000, however after Mr. McCune and Mr. Hyche
spoke to the NRCS, the emergency part was given back to the federal
agencies. Therefore, the agreement we
had you sign is no longer valid. They
are now looking to expand the program to include more than just emergency
cleanup and treating us similar to the municipal programs to include the roots
and trees on the banks, which is enticing.
The thought is we can get all of this completed in an improvement
program, where we would have the entire $3,000,000 or portions applicable to
collect from another agency. I am
cautious.
Mr. Hyche
stated the agreement from NRCS was emailed to me with the new scope.
Mr. Petty stated Mr. McKune is working on this as well. We are going to identify where the second
phase of trees are.
Mr. Fennell stated we have to look
at a short term loan scenario in case we have to go out and raise more money.
Mr. Petty stated we received
instruction from the Board at the first meeting where we discussed this. Ms. Janice Larned who is the Treasury Officer
for Severn Trent has experience beyond anything we have ever had in our company
before. She is on top of this issue. We have commercial banks vying to do business
with you for the short term cashflow at a rate meeting
the Florida League of Cities rate. This
is an unheard of precedent where we have commercial paper at the same level of
what the counties have available to them in this trust.
Mr. Fennell asked how much?
Mr. Petty responded on a one to one
ratio, equal to one year’s annual assessments.
This is what we asked them to review and approve for cashflow
purposes only. It does not mean we
cannot get a two to one or three to one or four to one. This is for cashflow
purposes without reapplying. They are
doing the one to one in advance before receiving the exact number from the
engineer.
Mr. Hanks asked at what interest
rate?
Mr. Petty responded 3.9%. The cost of issuance is down to $4,500. This is a fine instrument for the bonds. The people we have worked with over the 30
years are unbelievably efficient, however, this is not the case for this
District. We need short term cashflow. The deal
so far with the bank is within two weeks of signing the papers, we receive the
cash. It is an interest only loan until
October 1st or 365 days, whichever comes first at whatever term you
deem applicable up to five years. We
would roll it and fix it at that time.
However, once you fix it, your one to one ratio is now free and clear
for the next emergency.
Mr. Fennell asked do we have a Line
of Credit?
Mr. Petty responded this is the one
to one ratio we are trying to lock into, which is basically a revolving loan to
be tied into your budget and becomes free again for whatever necessary items
you may need. The one to one ratio is a
start number. For cashflow
purposes, this should be sufficient for these circumstances and gives us the
opportunity to do the application for the long term in a timely fashion. This note can evolve into a longer term note
with additional monies. Keep in mind, we
are not just limited to the General Fund.
We also have the exposure on the facility and utilities. The Utility Fund Budget would come into play
as well.
Mr. Hanks asked is there a reason
why we could not make an internal loan from the water and sewer to the General
Fund?
Mr. Petty responded we have done the
analysis and this is one option we will present to you at the next meeting. We know the short term commercial paper is
the best in our perspective but you have the option of looking at financing. The drawback is it would stop some of your
construction. If you take money out of
reserves, your cash is gone and you never want to reduce your cash.
Mr. Fennell stated Mr. Hanks has a
great point as we have money sitting in the bank, which we can loan to
ourselves, depending on the rate of return.
Mr. Hanks asked what is the current
rate of return on the $7,000,000 in the Construction Fund?
Mr. Petty responded I did not look
it up before coming to the meeting but I am sure it will be in our cashflow analysis.
It will probably not be anything exciting. If you want to do an intrafund
transfer we would be glad to go over the pros and cons with you. However, we request you not make a decision
at today’s meeting until you hear those pros and cons and the options available
to you.
Mr. Hanks asked can we increase our
water and sewer rates?
Mr. Lyles responded we can adjust
our rates through a public hearing mechanism and adopt a resolution
establishing a new set of rates, which could take effect immediately. You adopted a budget covering this entire
fiscal year. All we need is a
reconciliation to the budget and adopt an amended budget toward the end of the
current fiscal year. We could impose the
rates by following the process outlined in our special act.